Client: Benham Constructors Project Status: Complete
Project Start: September 2010 Project Completion: March 2011
Project Managers: Jim Rhodes Superintendents: Josh Akers
 

 

Wayne Brothers began this project in September 2010 at Boral Composites in Salisbury, NC. WBI completed both the grading and the concrete, and saved the project over two weeks by coordinating these two processes together. Our scope of work included mass grading for the six acre site, erosion control, water, storm sewer, fine grading, foundations, slab-on-grade, slab-on-metal deck, equipment pads and 50,000 square feet of concrete paving. We were very excited to work with SAIC, and to utilize both our grading and concrete teams.

 

 

"When you complete a 9 1/2 month project on time, on budget and with a perfect safety record, how can you expect more?"
   - Bill Kelsey,

      SAIC, Senior Project Manager